Zhejiang J&J Mobility Co., Ltd. annual output of 100,000 electric wheelchair production line technical renovation project environmental impact assessment information disclosure

1. Construction project overview
1. Project name: Zhejiang J&J Mobility Co., LTD., annual output of 100,000 electric wheelchair production line technical renovation project
2. Construction nature: new construction
3. Construction location: Baiyang Avenue, Baiyang Industrial Development Zone, Wuyi Economic Development Zone, Jinhua City, Zhejiang Province (in Zhejiang Fanen Smart Home Co., Ltd.)
4. Construction content: project leasing wuyi economic development zone white industrial function of Zhejiang pan on intelligent household co., LTD. Factory, using carbon steel, aluminum, paint and other raw materials, cutting, welding, coating process, purchase spray painting line, spray line, laser cutting machine equipment, after the completion of the annual output of 100000 electric wheelchair production capacity.
2. Distribution of major environmental sensitive targets within the scope of EIA
Table 1 List of major environmental protection targets near this Project
order number name coordinate Protect the content Environmental functional area Relative site orientation Relative to the factory boundary distance
east longitude northern latitude
1 Wynn gold 119.867812° 28.935853° settlement Class II functional area To the southwest 370m
2 Lower Chen village 119.877441° 28.931489° settlement Class II functional area To the southeast 394m
3. Major environmental impact forecast situation
(1) Impact of atmospheric environment
According to the engineering analysis, during the normal operation of the project, the impact of the pollutants discharged by each pollution source on the sensitive points of the surrounding environment and the regional environmental air quality is within the acceptable range, and has little impact on the surrounding environment.
(2) Water environment impact analysis
Achieve rain and pollution diversion. After the production wastewater, the domestic sewage together with the Wuyi city sewage treatment plant, and finally discharged into the Wuyi River. Under normal circumstances, the wastewater discharged by the project will not impact the Wuyi city sewage treatment plant. Under the premise of reaching the standard discharge, the wastewater discharge will not have a significant impact on the final sewage body Wuyi River, and the water quality of Wuyi River can basically maintain the status quo.
(3) Noise impact analysis
According to the forecast, the noise contribution value of the noise generated by the project after sound insulation and distance attenuation can meet the requirements of the three standards in the Environmental Noise Emission Standard for Industrial Enterprises (GB12348-2008), which has little impact on the sound environment of the factory boundary and will not have a significant impact on the sound environment of the factory boundary.
(4) Solid waste impact
All kinds of production solid waste produced by this project can be properly treated, and it is not expected to have a significant impact on the environment.
(5) Environmental risk impact
Under the condition of good environmental risk prevention measures, the environmental risk of this project can be controlled, and the risk level of environmental accidents is acceptable.
Iv. Major environmental protection measures, environmental risk prevention measures and the expected results
Table 2. Main pollution prevention and control measures
classify pollutant source Pollutant project Environmental protection measures operative norm
exhaust gas weld fumes particulate matter Strengthen the ventilation at the top of the workshop It meets the unorganized emission standard in Table 2 of GB16297-1996 Comprehensive Emission Standard for Air Pollutants
Throw pill dust particulate matter It is collected and treated through the cloth bag dust collector and discharged at high altitude It meets the emission standard in DB33 / 2146-2018 Emission Standard for Air Pollutants in Industrial Coating Process and Table A in Appendix A of GB37822-2019 Dismission Control Standard of Volatile Organic Organics. Special emission limits of 1
Spray plastic waste gas particulate matter Collect and recycle through filter element + bag dust removal device and lead to high altitude discharge
Cure waste gas Non-methane total hydrocarbon The gas collecting hood is set above the drying opening
Spray paint exhaust gas, drying exhaust gas Non-methane total hydrocarbon, butyl acetate, odor Spray paint waste gas after water curtain pretreatment and drying waste gas by the “cyclone tower spray + dry filtration + activated carbon adsorption and concentration + catalytic combustion desorption regeneration” treatment after high altitude discharge
Gas flue gas particulate matter, SO2、NOX, Lingman smoke blackness After collection, it is discharged at high altitude along with the exhaust gas exhaust cylinder of the corresponding process The Implementation Plan for Comprehensive Control of Air Pollution in Industrial Furnaces of Zhejiang Province no. 315,2019 and the corresponding standards in the Emission Standard of Air Pollutants in Industrial Furnaces (GB 9078-1996)
waste water sanitary waste CODcr 、NH3-N After the septic tank pretreatment, it will be treated in the urban sewage treatment plant It meets the tertiary standard of GB 8978-1996 Comprehensive Sewage Discharge Standard and the Indirect Discharge Limits of Nitrogen and Phosphorus Pollutants in Industrial Enterprises (DB 33 / 887-2013)
factory effluent CODcr, Petroleum, SS, LAS A certain amount of dilute sulfuric acid and Fenton reagent were added to reduce the concentration of CODcr, and then the sewage treatment station of Zhejiang Fanen Intelligent Home Co., Ltd. for oil isolation, regulation, flocculation precipitation, sand filtration and other treatment and then the standard in the urban sewage treatment plant
noise Operation of mechanical equipment and environmental protection facilities Equivalent continuous A sound level Select noise reduction equipment, local sound insulation, add muffler and other facilities to high noise equipment air compressor, strengthen equipment maintenance. It meet the GB 12348-2008 “Industrial Enterprise Environmental Noise Emission Standard”
solid waste Collect the metal scraps and shot dust; recycle the collected plastic powder dust and reuse; entrust the sanitation department to clean the waste, waste residue, waste packaging bucket, waste activated carbon, waste catalyst and waste filter cotton.
V. Preliminary conclusions of environmental impact assessment
The project conforms to the “three lines and one order” ecological environment zoning control scheme of Wuyi County, the relevant industrial national and local policies, and the site selection conforms to the overall planning and land use planning; the discharge of pollutants can meet the total access requirements, the pollutants have little impact on the local environment after treatment, and all environmental elements can maintain the existing functional requirements; the impact of project construction on the surrounding environment and environmental risks can be controlled within the acceptable range. Therefore, from the perspective of environmental protection, the project as long as the implementation of the eia proposed governance measures, the implementation of environmental protection investment, the strict implementation of the “three simultaneous” system, in the safety of production to ensure the pollutant emission standards, strengthen environmental management, the implementation of the project is feasible.
6. Method and duration of public access to eia documents
If the public need to consult the eia documents, please bring their ID cards to Zhejiang Xiao Environmental Technology Co., Ltd. or the construction unit within 10 working days of the announcement period. The public can also put forward suggestions or opinions on the project construction in the form of visitors, calls and letters.
7. Scope and object of soliciting public opinions
The scope and object of soliciting public opinions are the target public of environmental protection within the scope of environmental impact assessment.
Viii. Specific forms of soliciting public opinions
Take the form of the public display board around the project and the public website.
Time for publicity and public comment: From April 15 to April 28,2024.
9. Contact information of local environmental protection departments, eia units and project construction units
(1) Construction unit: Zhejiang J&J Mobility Co., LTD. Address: Wuyi Industrial Development Zone Baiyang Industrial Functional Zone Tel: 13858945519
(2) Eia unit: Zhejiang Xiao Environmental Technology Co., LTD. Address: Huanglong Third Road, Huanglong Industrial Zone, Wuyi Tel: 13857926129
(3) Examination and approval department: Wuyi Branch of Jinhua Ecological Environment Bureau Address: Third floor of Wuyi County Administrative Service Center Tel: 0579-87673710
Issued by: Zhejiang J&J Mobility Co., LTD